Production schedule will follow the above schedule for daily printing fabric production for each type of fabric
Schedule will be allocated D+2 after payment is received, maximum at 3 pm on Monday – Friday, and at 9 am on Saturday. If payment is received after the specified time then fabric production will follow the next schedule
Summary of the cut-off payment time:
In order to be processed on Monday, payment need to be done before Friday at 3 pm
In order to be processed on Tuesday, payment need to be done before Saturday at 9 am
In order to be processed on Wednesday, payment need to be done before Monday at 3 pm
In order to be processed on Thursday, payment need to be done before Tuesday at 3 pm
In order to be processed on Friday, payment need to be done before Wednesday at 3 pm
In order to be processed on Saturday, payment need to be done before Thursday at 3 pm
Example of Tencel production:
Customer order Tencel fabric on Wednesday and payment is done on Wednesday 12 pm, then fabric production will start on Friday
Customer order Tencel fabric on Wednesday and payment is done on Wednesday 4 pm, then fabric production will start on Tuesday (fabric will be allocated D+2 after payment, in order to be processed on Friday payment need to be done before Wednesday 3 pm)
Customer order Tencel fabric on Monday and payment is done on Monday 12 pm, then fabric production will start on Friday (fabric will be allocated D+2 after payment is received)
Customer order Tencel fabric on Saturday and payment is done on Saturday 9 am, then fabric production will start on Tuesday
Customer order Tencel fabric on Saturday and payment is done on Saturday 11 am, then fabric production will start on Friday (the cut-off time for is Saturday 9 am)
Production schedule cannot be changed and applies to all fabric production including test print and fabric production 1 meter and above